Bill of materials (BOM)
A bill of materials (BOM) is a structured list of the parts, raw materials and subassemblies needed to make a product, with their quantities and units of measure. It tells a business what goes into the product, not what a customer owes.
How it works
Each line identifies an item by part number and description, then states how much is needed for one finished unit or a specified batch.
A single-level BOM lists the product's immediate components. A multi-level BOM also breaks subassemblies into their component parts. An engineering BOM describes the design; a manufacturing BOM organizes what production needs to build it.
Tie each BOM to a product revision. If a hardware startup changes its battery but purchasing uses the old BOM, it can order parts that no longer fit.
Materials for 100 sensors cost $1,720
A startup plans to build 100 identical sensors. These illustrative prices exclude assembly labor, overhead and shipping. There is no scrap or existing inventory.
| Part | Quantity per sensor | Unit cost | Cost per sensor |
|---|---|---|---|
| Circuit board | 1 | $12.00 | $12.00 |
| Enclosure | 1 | $3.00 | $3.00 |
| Battery | 1 | $2.00 | $2.00 |
| Screw | 4 | $0.05 | $0.20 |
Material cost per sensor = $12 + $3 + $2 + (4 × $0.05) = $17.20.
For 100 sensors: 100 × $17.20 = $1,720. Purchasing needs 100 boards, 100 enclosures, 100 batteries and 400 screws.
That is the material cost, not total cost of goods sold. Treating it as the full production cost would overstate the startup's gross margin.
Questions people ask
Does a bill of materials need cost?
No. A BOM can specify parts and quantities without prices. A costed BOM adds unit costs and calculated totals. Before using it for budgeting, check which costs it includes and when prices were last updated.