Earned value management (EVM)
Earned value management (EVM) is a project-control method that compares the budgeted cost of completed work with planned work and actual costs. It measures cost and schedule performance against an approved plan, rather than judging progress by money spent or time elapsed.
How it works
Start with a time-phased budget and measurable definitions of completed work. At each reporting date, calculate:
- Planned value (PV): the budgeted cost of work scheduled.
- Earned value (EV): the budgeted cost of work actually completed.
- Actual cost (AC): costs incurred for the work performed.
Earned value is not revenue, profit or company valuation. For startups, EVM fits defined hardware or customer implementation projects better than open-ended product discovery.
Spending $60,000 to complete $40,000 of planned work
A project has a $100,000 total budget. By today, 50% of the budgeted work should be complete. Only 40% is complete, measured by its budgeted value, and costs incurred total $60,000.
| Measure | Calculation | Result |
|---|---|---|
| Planned value | $100,000 × 50% | $50,000 |
| Earned value | $100,000 × 40% | $40,000 |
| Actual cost | Recorded costs | $60,000 |
| Cost variance | EV − AC | −$20,000 |
| Schedule variance | EV − PV | −$10,000 |
The project has incurred $20,000 more than the budgeted cost of the work delivered. It has also completed less work than planned. Schedule variance measures that shortfall in dollars, not days late.
The distinction matters: spending 60% of the budget does not mean the project is 60% complete.
Questions people ask
What are BAC and EAC in project management?
Budget at completion (BAC) is the total approved project budget. Estimate at completion (EAC) is the forecast total cost. If current cost efficiency continues, EAC = BAC ÷ (EV ÷ AC). Here, $100,000 ÷ ($40,000 ÷ $60,000) = $150,000. That means another $90,000 is needed beyond the $60,000 already incurred, although only $40,000 remains in the original budget. This forecast assumes unchanged scope and continuing cost efficiency; it is not an approved budget increase.