Notice to proceed
Also called an NTP.
A notice to proceed (NTP) is a formal instruction authorizing a contractor to start specified work under a contract. It often starts the clock for completing that work, especially in construction.
How it works
The owner or an authorized representative issues the notice after the contract is signed and required conditions, such as insurance or bonding, are satisfied. The contract determines whether time runs from receipt of the notice, a stated effective date, or another event.
A contract award selects the contractor; an NTP authorizes performance. They are not necessarily simultaneous. Starting early can leave the contractor exposed to costs the owner has not authorized.
A limited notice to proceed authorizes only specified work, such as ordering equipment or preparing the site. It is not permission to complete the entire project.
A 10-day delay moves a 60-day deadline
An office fit-out contract requires completion 60 calendar days after receipt of the NTP, excluding the receipt day. Here are two possible schedules:
| NTP received | Calculation | Completion due |
|---|---|---|
| June 1 | June 1 + 60 calendar days | July 31 |
| June 11 | June 11 + 60 calendar days | August 10 |
The later notice shifts the deadline by 10 days. It does not reduce the contractor's work period to 50 days. If the contract instead sets a fixed completion date, a delayed NTP does not automatically move that date.
What the document says
In US federal construction contracts, FAR 52.211-10 ties commencement to a specified number of calendar days after receipt of the NTP and separately sets the completion requirement.
Read the notice alongside the contract. Check the authorized scope, timing and any limits before committing labor or ordering materials.
Questions people ask
Is a notice to proceed legally binding?
An NTP issued by an authorized person under a binding contract can trigger enforceable performance obligations. Its effect depends on the contract; it does not automatically replace or amend it.
What does a notice to proceed look like?
It is usually a letter or formal notice identifying the project, contract, authorized work and applicable start date. It should make clear whether authorization is full or limited.